Makripodis College Mid-Way Build Update



Praise The Lord! What a massive amount of progress has occurred with the Makripodis College build.


Let's travel back in history to see the overall timeline for this trip.


End of Jan to the beginning of Feb.

Final concrete footers poured. Main building end and frame columns were erected and attached to end wall rafters.


concrete footers
concrete footers

adding steel beams to concreate footers
adding end wall rafters


Saturday the 3rd of Feb

Three roof pitch sections were completed and purlins were added to two roof segments.

two frame segments purlined
two frame segments with purlins added


Sunday the 4th of Feb

Three roof pitch segments were completed with purlins.

three frame segments with purlins of weo college
three frame segments completed with purlins

Tuesday the 6th of Feb

Left-college wing end and frame columns were erected and purlins added

left wing framed and purlins added
left-wing framed and purlins added

Today the 8th of Feb

College right-wing end and frame columns were erected, end wall girt completed, entrance framing and purlins added


entrance support beams added
entrance support beams added

God bless all the hard volunteers/workers who are pushing through the intense elements to build the college at such an impressive rate. It is going to be such a blessing to many Africans to come! Thank you for all your support and prayers as well.


Thanks to WEO president Dan Yanchak for providing the drone for the aerial photos and videos. Thank you Mike Makripodis for making the pre-engineered building possible.


Please continue to pray for the team as they are just over halfway through their time in Africa for this build.